Exterior- Scope of work to include painting of front clapboards and trim on house
Soft wash
Front of house will be soft washed using a mild bleach, TSP, and Dawn dish detergent mixture to remove dirt and mildew. Because we are not painting the shingles on the side of house, we will not be soft washing them.
Trim
Trim areas on sides and back of house will be washed by hand as needed to remove dirt and mildew.
Once thoroughly dry, all trim on home will be scraped and sanded as needed.
All open joints, gaps, and seams will be caulked.
Bare areas will be spot primed.
We will apply 2 complete coats of Sherwin Williams Satin Duration paint to all trim.
We noticed several rotted areas. We will replace rot at bottom of corner boards, bottom of garage door casings, and bottom of rake boards along roof. These areas will be replaced with PVC composite so they do not rot again.
While painting we will remove downspouts so we can paint behind them, then reinstall upon completion.
Clapboards
We will need to remove shutters.
Clapboards will be prepped and painted 2 coats of white in Sherwin Williams Flat Duration paint.
Upon completion we will rehang shutters.
This quote does not include painting shutters and it will be listed in a separate option below.
While painting we will take precautions to cover roofs, walkways, etc. to prevent paint spatter.
Labor and Materials: $7,500
Additional option- Shutters
While we are on site, if you would like the shutters primed and painted it would be an additional $350
Please note, vinyl windows and garage doors are maintainence free and will not be painted.
Please sign using a stylus, your mouse, or your finger below to authorize this contract. By electronically signing this document, you agree to the terms established above.
After the document is signed, you can proceed to print it or save it as a PDF.
Client Information
Signed by Ann Nash Perry on Fri Apr 18 2025 08:06:10 GMT-0400 (Eastern Daylight Time)
IP Address: 66.30.93.163